• Eastern Steel Annual Maintenance Last Day -- Each Production Process Has Completed ahead of Schedule

    On 21:58 of 20 September, Blast Oxygen Furnace has completed bricks stacking and baking furnace, then began refining at 23:28, all production process has resume to normal production. The 1st Annual Maintenance is completed successfully.

    Sintering has planned maintenance for 87 hours and the actual maintenance duration is 80 hours. It has begun from 17 September 7:32 until 20 September 15:32, total 7 hours ahead of schedule.

    Blast Furnace has planned maintenance for 78 hours and the actual maintenance duration is 71 hours and 26 minutes. The down 17 September 8:30 until 20 September 7:56, total 6 hours and 34 minutes ahead of schedule.

    Steel Making has planned maintenance for 100 hours and the actual maintenance duration is 96 hours and 8 minutes. The downtime was 16 September 21:50, baking furnace at 20 September 21:58 and resume refining at 23:28. Total 3 hours and 52 minutes ahead of schedule.

    Oxygen Making has planned maintenance for 63 hours and the actual maintenance duration is 52 hours and 15 minutes. The downtime was 16 September 16:15, nitrogen composition passed at 19 September 20:30. Total 10 hours and 45 minutes ahead of schedule.

    55MW Power Generation has planned maintenance for 95 hours and the actual maintenance duration is 84 hours and 30 minutes. It has begun from 17 September 6:59 until 20 September 19:29, total 10 hours and 30 minutes ahead of schedule.

    Written by: P&T Guan Yanjie